Search Topical
Work causing significant noise will begin near Kaskela during weeks 29 and 31
The construction of the Vantaa Light Rail near Kaskela area is entering a phase that will cause more noise than usual in the surrounding area. Sheet piling work on Kyytitie, near Pitkäsentie and Lahdentie, will start in mid-July, followed by hammer drilling in late July.
Crushing of Rock Material Causing Increased Noise to Begin at the Vaarala Depot
The crushing of rock material excavated at the Vaarala depot site will begin in July. The work will generate increased noise levels in the surrounding area. The work is scheduled to start in week 29.
Vaaralan Talkootie Bus Stop V9306 to Be Temporarily Relocated from 8 July Due to Light Railway Construction
The Vaaralan Talkootie bus stop (V9306) on Hakunilantie will be temporarily relocated from 8 July. The stop will move approximately 60 meters forward in the direction of travel along Hakunilantie.
High-noise work continues on Kyytitie between Santaradantie and Kanervatie
Rock excavation work at the construction site on Kyytitie between Santaradantie and Kanervatie has been largely completed. However, we may need to carry out work on individual days if additional rock areas requiring excavation or breaking are identified as the project progresses. In addition, rock
Vantaa becomes the first municipality in Finland to introduce the internationally recognised IB programme to early childhood education
The Y.E.S. Daycare Centre in Pakkala will begin piloting the International Baccalaureate (IB) programme in English in autumn 2026.
Notice of blasting work on Pitkäsentie during Week 28
During drilling work on Pitkäsentie, a rock formation has been discovered, and as a result, blasting work will be carried out in the area during Week 28.
Drilling and excavation works causing significant noise will expand on Hakunilantie to the Kyytitie intersection
The excavation works currently underway on Hakunilantie will expand to the section between Raudikkokuja and Kyytitie in week 28. Drilling and trench excavation will be carried out in the area, causing significant noise.
Blasting works will affect parking and traffic near Laukkarinne and Kyytitie during week 28
Blasting work will be carried out during the daytime in week 28 in the area connecting Laukkarinne and Kyytitie. The work requires the nearby parking area to be cleared and will cause short traffic interruptions during blasting.
Temporary Traffic Arrangements Introduced on Lemmenkuja
Construction works at the Vaarala depot have progressed to Lemmenkuja, and from week 26 onwards, temporary traffic arrangements have been implemented. These arrangements will be modified as the work progresses.
Introduction of a temporary access ramp to Tikkuparkki
Construction of the Vantaa light rail is ongoing in Kirjastopuisto. According to current plans, a temporary access ramp to Tikkuparkki will be introduced on 10 July. It is located next to the current ramp, closer to the library. Tikkuparkki will operate as normal throughout the construction period.