Construction of the Vaarala Depot Building Begins in December – Ground Source Heat Wells to Be Drilled as the First Phase
Construction of the Vaarala Depot is moving into its next phase as work on the depot building begins in December 2026. The first construction activities on site will include drilling ground source heat wells and building foundations. The works may cause noise and occasional vibration in the
Works causing particularly loud noise on the Länsimäentie section of Vantaa light rail during November and December
Construction of Vantaa light rail is progressing, and in week 49, demolition of the old bridge and construction of a new one will begin on Länsimäentie, near Maratontie and the Vartiotie roundabout.
Porttisuontie and Kyytitie intersection to be closed overnight for three nights, 7–9 December 2026
As part of the Vantaa light rail project, adjustment works related to road surface levels will be carried out at the Porttisuontie and Kyytitie intersection from 7 to 9 December 2026.
Temporary detour on the Kyytitie pedestrian and cycling path between Jokiniemenkatu and Kanervantie on 30 November–1 December
As previously announced, the section of the Vantaa light rail route from Heidehof Park to Kanervantie will open to traffic ahead of schedule. As part of the opening, we will complete the final surfacing of the pedestrian and cycling path. The crushed stone surfaces will be levelled, and the path
Vantaa light rail continues excavation works on Länsimäentie near the Vaarala depot
Vantaa light rail will continue excavation works on Länsimäentie along the future straight section leading to the Vaarala depot, where more rock than expected has been encountered. Excavation works in the area are progressing quickly, as the subsequent work stages cannot proceed until the excavation
Concreting of the new bridge over Porvoo Highway will cause changes to traffic arrangements
Concreting of the deck of the new bridge over Porvoo Highway will begin on Tuesday, 1 December, at 7:00 a.m. and continue until Wednesday morning, 2 December. The estimated duration of the concreting work is approximately 24 hours. The concrete must be poured continuously, which means that work at
Piling Works Underway on Hakunilantie – Earplugs Available Near the Construction Site
Piling works have begun on Hakunilantie, south of Ring III in Vaarala. The works will continue throughout November and December and will occasionally cause noise in the surrounding area. Earplugs are available for people passing through the area at bus stops located near the construction site.
Construction of the Vantaa light rail bridge begins – traffic arrangements also on Tuusulanväylä
Vantaa Light Rail will build a new light rail bridge on Tikkurilantie over Tuusulanväylä. Work will begin on the Tuusulanväylä side on 1, December. Speed limits will be reduced at the construction site. In addition, the locations of bus stops will change.
The First Rails Have Been Installed on Hakunilantie!
The first rails are now in place on Hakunilantie.
The Kyytitie street section between Jokiniemenkatu and Kanervantie to open to traffic eight months ahead of schedule
Construction of the Vantaa light rail is progressing ahead of schedule on Kyytitie. The street section between Jokiniemenkatu and Kanervantie, built by the East Alliance formed by Kreate and GRK, will open to traffic on Monday, 7 December 2026. The street will be brought into use as much as eight