The First Rails Have Been Installed on Hakunilantie!
The first rails are now in place on Hakunilantie.
The Kyytitie street section between Jokiniemenkatu and Kanervantie to open to traffic eight months ahead of schedule
Construction of the Vantaa light rail is progressing ahead of schedule on Kyytitie. The street section between Jokiniemenkatu and Kanervantie, built by the East Alliance formed by Kreate and GRK, will open to traffic on Monday, 7 December 2026. The street will be brought into use as much as eight
Water Main Drilling Works to Begin on Fazerintie in Week 47
A water main will be constructed beneath Fazerintie during week 47. The work will be carried out using a percussion drilling method, which allows the water main to be installed under the road without extensive excavation of the street or major traffic arrangements.
Invitation to residents: The first tram rails will be installed on Kielotie on 18 November 2026
Vantaa Light Rail will install the first tram rails in the Tikkurila city centre worksite area on Kielotie. We invite residents and others interested in the topic to come and watch the installation of the rails on 18 November 2026.
The winners of the international Tikkurila station art competition are Johanna Rytkölä and Seera Love
The Vantaa light rail’s international art competition has ended. The impressive and colorful Clayflow was chosen as the winner from among 150 proposals. The work brings a new look to the architecture of the station and draws inspiration from the history of Tikkurila and Vantaa.
Piling works causing significant noise to begin in week 47 on Hakunilantie south of Ring III
Piling works will commence in week 47 on Hakunilantie, south of Ring III. The work phase will cause intermittent noise and vibration in the vicinity of the work area during November and December.
Changes to the Tikkurilantie construction sites from 9 November
The Vantaa Light Rail construction site on Tikkurilantie will expand westwards, causing extensive changes to traffic arrangements in November and December 2026.
Water Utility Works Expand – Vaarala Talkootie Bus Stop Relocates from 11 November
The Vaarala Talkootie bus stop will be temporarily relocated to a new location starting Wednesday, 11 November. The stop is being moved due to the expansion of the work area for ongoing water utility construction works. The temporary stop will be located approximately 60 metres back in the direction
Vantaa Light Rail worksite expands to the southern section of Osuustie
Construction of the Vantaa Light Rail is already underway on the central and northern sections of Osuustie. According to current plans, the worksite will also expand to the southern section of Osuustie, near the intersection with Väinö Tannerin tie, during the week starting 23 November. Changes will
Noisy construction work continues on Länsimäentie next week
Next week (week 46), the previous sheet piling works will be followed by piling works as part of the construction of the water and sewer network.