Construction of the Vaarala Depot Building Begins in December – Ground Source Heat Wells to Be Drilled as the First Phase
Construction of the Vaarala Depot is moving into its next phase as work on the depot building begins in December 2026. The first construction activities on site will include drilling ground source heat wells and building foundations. The works may cause noise and occasional vibration in the surrounding area.
Construction Work Begins
On 23 November 2026, SRV and Pääkaupunkiseudun Kaupunkiliikenne Oy announced that they had signed the implementation phase contract for the construction of the Vaarala depot building.
Since June 2026, the Ratapiha-allianssi has carried out preparatory rock excavation, earthworks and infrastructure works in the area. The alliance will continue with the works under its responsibility alongside SRV.
SRV will begin work by expanding the site facilities starting on 1 December 2026. The first construction activities will commence on 2 December 2026 with the drilling of ground source heat wells and the construction of cast-in-place strip foundations.
No changes to traffic arrangements in the area are expected before the end of the year.
Noise and Vibration from Ground Source Heat Well Drilling
The drilling of ground source heat wells and foundation works will continue beyond the turn of the year into 2027. The drilling work is expected to be completed by the end of January, and the installation of the associated collector pipe network will continue through February.
The drilling of the heat wells may cause noise and vibration in the surrounding area. Noise-generating work will mainly be carried out on weekdays between 7:00 a.m. and 6:00 p.m.
If particularly disturbing indoor noise is experienced in nearby properties, please contact us at viestinta@vantaa.fi. We can provide hearing protection if needed.
We apologize for any inconvenience caused by the works.
The location of the Vaarala depot is shown on the map below.
Work Progresses in Stages
Installation of the depot building’s precast concrete frame will begin in January-February 2027 and will proceed in parallel with the foundation works.
The frame installation will start with the installation of hollow-core slab, column and beam concrete elements. Installation of the timber roof elements for the tram halls and the façade elements will begin later in spring 2027.