Work causing significant noise will begin near Kaskela during weeks 29 and 31
The construction of the Vantaa Light Rail near Kaskela area is entering a phase that will cause more noise than usual in the surrounding area. Sheet piling work on Kyytitie, near Pitkäsentie and Lahdentie, will start in mid-July, followed by hammer drilling in late July.
Crushing of Rock Material Causing Increased Noise to Begin at the Vaarala Depot
The crushing of rock material excavated at the Vaarala depot site will begin in July. The work will generate increased noise levels in the surrounding area. The work is scheduled to start in week 29.
Vaaralan Talkootie Bus Stop V9306 to Be Temporarily Relocated from 8 July Due to Light Railway Construction
The Vaaralan Talkootie bus stop (V9306) on Hakunilantie will be temporarily relocated from 8 July. The stop will move approximately 60 meters forward in the direction of travel along Hakunilantie.
High-noise work continues on Kyytitie between Santaradantie and Kanervatie
Rock excavation work at the construction site on Kyytitie between Santaradantie and Kanervatie has been largely completed. However, we may need to carry out work on individual days if additional rock areas requiring excavation or breaking are identified as the project progresses. In addition, rock
Drilling and excavation works causing significant noise will expand on Hakunilantie to the Kyytitie intersection
The excavation works currently underway on Hakunilantie will expand to the section between Raudikkokuja and Kyytitie in week 28. Drilling and trench excavation will be carried out in the area, causing significant noise.
Blasting works will affect parking and traffic near Laukkarinne and Kyytitie during week 28
Blasting work will be carried out during the daytime in week 28 in the area connecting Laukkarinne and Kyytitie. The work requires the nearby parking area to be cleared and will cause short traffic interruptions during blasting.
Temporary Traffic Arrangements Introduced on Lemmenkuja
Construction works at the Vaarala depot have progressed to Lemmenkuja, and from week 26 onwards, temporary traffic arrangements have been implemented. These arrangements will be modified as the work progresses.
Pedestrian overpasses on Hakunilantie to be demolished in June – works carried out at night
The demolition of the pedestrian overpasses on Hakunilantie at Hakunila shopping centre (Kaviopolku), Raudikkopolku, and Hevoshaanpolku will be carried out in three phases in June. The work will take place at night. The demolition is not expected to cause significant noise in the area.
Ground stabilization work causing significant noise will begin in June at the southern end of Hakunilantie
Ground stabilization works will begin at the southern end of Hakunilantie in week 26. The work is estimated to continue until the end of August 2026. The work will cause significant noise in the area as well as changes to traffic arrangements. As part of these changes, the bus stop on Vaaralantie
Noisy work phases planned on the median strip of Porvoonväylä at Länsimäentie and in the Maratontie area in July–August
On the Porvoonväylä at the intersection with Länsimäentie and near the Maratontie roundabout, work will be carried out during the summer that will cause noise. At the turn of June and July, rock blasting will take place in the central lanes, which may result in loud noise and temporary traffic