Tag: Vantaa Light Rail Kuninkaala - Mellunmäki

Construction Progressing as Planned at the Vaarala Depot

News

Earthworks at the Vaarala Depot have progressed on schedule over the summer, and the area is gradually beginning to take its final shape. Most of the rock excavation has now been completed, and work is currently focused on foundation structures, municipal infrastructure, and stormwater systems

Hakunila major region

Drilling and rock excavation works causing elevated noise levels to begin in the area between Lahdentie and Liinakkokuja

News

Rock drilling and rock excavation works will begin in September in the area north of Kyytitie, between Lahdentie and Liinakkokuja, due to a rock formation uncovered during construction. The works will cause noise and vibration in the surrounding area. The drilling and rock excavation works are

Hakunila major region

Hepopolku Bus Stop on Hakunilantie Returns to Its Original Location on 14.9.

News

The new street connection being built on the eastern side of Hakunilantie has progressed to a stage where the Hepopolku bus stop can be returned to its permanent location. At the same time, the temporary bus stop used during construction will be removed from service. The final bus shelter and

Hakunila major region

Vantaa Light Rail makes use of deadwood and forest floor material as nature and construction are reconciled

News

Construction inevitably changes the environment, but biodiversity can be supported in many ways, even in major infrastructure projects. At the Vantaa Light Rail construction site on Rivieranraitti, taking nature into account is reflected, for example, in leaving deadwood in the area’s natural

Hakunila major region

Preparing for Asphalt Paving and New Traffic Arrangements on Hakunilantie

News

Construction on Hakunilantie is progressing into a highly visible phase this autumn as work moves from kerb and stone installation to asphalt paving. Once paving is completed, traffic will be transferred to the new traffic lanes, and construction will continue on the western side of the street with

Hakunila major region

A particularly noisy phase of the work will begin in week 37 on Länsimäentie near the Maratontie roundabout

News

The particularly noisy work will continue for approximately 15 days, on weekdays between kl. 7–18

Rock Drilling and Excavation Works Causing Increased Noise to Continue on Hakunilantie

News

Rock drilling and excavation works that began in June on Hakunilantie, between Kyytitie and Tammapolku, will continue. The excavation works need to be extended beyond the original estimate, as more bedrock than anticipated has been encountered within the work area, increasing the extent of rock

Hakunila major region

Keihästie closed to vehicle traffic at the intersection with Länsimäentie from 28 September to 9 October 2026

News

Keihästie closed to vehicle traffic at the intersection with Länsimäentie from 28 September to 9 October 2026

Noisy Drilling and Rock Excavation Works to Begin on Rivieranraitio

News

Rock and stone drilling as well as rock excavation works will begin in September along the future tramway street connection on the Rivieranraitio. The works will cause significant noise in the area. The works are scheduled to start in Week 36.

Hakunila major region

Gas pipeline construction work continues in Heidehof Park – changes to pedestrian routes as work progresses

News

In addition to the construction of the Vantaa light rail, preparatory and construction works related to gas transmission company Gasgrid’s high-pressure gas pipeline, as well as the construction of a pressure reduction station, will be carried out in the area during weeks 35–46.