Minor changes to traffic arrangements at the Vanha Porvoontie and Kyytitie roundabout on Tuesday, 1 December 2026 – the changes will be implemented the previous night

News

Construction works at the Vanha Porvoontie and Kyytitie intersection are progressing into new areas as excavation works in the previous areas have been completed. As a result, minor changes will be made to traffic arrangements.

Tikkurila major region

Night works on Kyytitie between Vanha Porvoontie and Porttisuontie from 30 November to 2 December 2026

News

Night works will take place on the night of Monday 30 November to Tuesday 1 December, and on the night of Tuesday 1 December to Wednesday 2 December.

Tikkurila major region

Construction of the Vaarala Depot Building Begins in December – Ground Source Heat Wells to Be Drilled as the First Phase

News

Construction of the Vaarala Depot is moving into its next phase as work on the depot building begins in December 2026. The first construction activities on site will include drilling ground source heat wells and building foundations. The works may cause noise and occasional vibration in the

Hakunila major region

Works causing particularly loud noise on the Länsimäentie section of Vantaa light rail during November and December

News

Construction of Vantaa light rail is progressing, and in week 49, demolition of the old bridge and construction of a new one will begin on Länsimäentie, near Maratontie and the Vartiotie roundabout.

Hakunila major region

Porttisuontie and Kyytitie intersection to be closed overnight for three nights, 7–9 December 2026

News

As part of the Vantaa light rail project, adjustment works related to road surface levels will be carried out at the Porttisuontie and Kyytitie intersection from 7 to 9 December 2026.

Tikkurila major region

Temporary detour on the Kyytitie pedestrian and cycling path between Jokiniemenkatu and Kanervantie on 30 November–1 December

News

As previously announced, the section of the Vantaa light rail route from Heidehof Park to Kanervantie will open to traffic ahead of schedule. As part of the opening, we will complete the final surfacing of the pedestrian and cycling path. The crushed stone surfaces will be levelled, and the path

Tikkurila major region

Vantaa light rail continues excavation works on Länsimäentie near the Vaarala depot

News

Vantaa light rail will continue excavation works on Länsimäentie along the future straight section leading to the Vaarala depot, where more rock than expected has been encountered. Excavation works in the area are progressing quickly, as the subsequent work stages cannot proceed until the excavation

Hakunila major region

Concreting of the new bridge over Porvoo Highway will cause changes to traffic arrangements

News

Concreting of the deck of the new bridge over Porvoo Highway will begin on Tuesday, 1 December, at 7:00 a.m. and continue until Wednesday morning, 2 December. The estimated duration of the concreting work is approximately 24 hours. The concrete must be poured continuously, which means that work at

Hakunila major region

Piling Works Underway on Hakunilantie – Earplugs Available Near the Construction Site

News

Piling works have begun on Hakunilantie, south of Ring III in Vaarala. The works will continue throughout November and December and will occasionally cause noise in the surrounding area. Earplugs are available for people passing through the area at bus stops located near the construction site.

Hakunila major region

The First Rails Have Been Installed on Hakunilantie!

News

The first rails are now in place on Hakunilantie.

Hakunila major region