Service group: Transport

Invitation to Resident Information Sessions – Construction of the Vantaa Light Rail Begins on Hakunilantie opens in new window, links to another website

News

According to current plans, construction of the Vantaa Light Rail will begin on Hakunilantie in spring 2026. We will organise resident information sessions about the upcoming street construction works: one in Vaarala Chapel (Kirkkokuja 2) on 23 February from 18:00 to 19:00, and another in

Hakunila major region

New construction sites for the Vantaa light rail in the Väritehtaankatu area opens in new window, links to another website

News

The construction work for the Vantaa light rail is expanding in the Väritehtaankatu area. Some sections have already been fenced off for site use, and the work will begin with the relocation of municipal infrastructure. Work on the site will take place on weekdays between 7 a.m. and 6 p.m.

Tikkurila major region

Pedestrian and bicycle traffic will be closed on Kielotie between Asematie and Unikkotie opens in new window, links to another website

News

Pedestrian and cycle traffic will be closed on Kielotie between Asematie and Unikkotie due to the relocation of municipal infrastructure. All local shops and businesses will remain open as usual.

Tikkurila major region

Through‑traffic on Ratatie will come to an end opens in new window, links to another website

News

Construction of the Vantaa Light Rail is progressing in Tikkurila. Through‑traffic on Ratatie will end on 19 January, and at that time we will begin building new bus stops. The works are related to the construction of the light rail tunnel.

Tikkurila major region

The Tikkurila bus terminal is moving in February

News

The light rail tunnel will eventually run under the Tikkurila bus terminal, which is why the buses must move elsewhere for the duration of the construction. According to the current information, this change will take place in early February 2026.

Tikkurila major region

The light rail construction sites are expanding in December

News

The Vantaa light rail construction sites have impacted the lives of residents in Tikkurila’s center since the spring. In December, the construction of the light rail will begin to cover a significantly larger area.

Aviapolis major region Hakunila major region Tikkurila major region

Tikkurilantie will be closed to through traffic between Puutarhatie and Kielotie starting January 7th, 2026 opens in new window, links to another website

News

Due to the construction phase of the Vantaa light rail, we will gradually close Tikkurilantie to through traffic starting in January. In the first phase, we will work between Puutarhatie and Kielotie. This section of Tikkurilantie will be closed to through traffic, and works will begin on January

Tikkurila major region

Light rail line 15 captured the hearts of passengers

Article

In Helsinki, the clanking of tram cars has been heard for over 100 years, but the first light rail line only began operating in October 2023 – and with none of the clanking.

Construction of the Vantaa Light Rail begins on Kyytitie in December opens in new window, links to another website

News

Construction of the Vantaa light rail will begin on Kyytitie in December. During the first phase in December 2025, work will take place on three sections of Kyytitie. Work in the area will continue until 2029.

Tikkurila major region

Building of Vantaa light rail progresses full speed ahead in December - implementation agreement signed opens in new window, links to another website

News

Building of Vantaa light rail will really get going in December 2025, when the light rail alliance’s implementation stage begins. The alliance partners signed the agreement on the implementation stage on November 26, 2025.

Aviapolis major region Hakunila major region Tikkurila major region