Service group: Transport
Drilling and excavation works causing significant noise will expand on Hakunilantie to the Kyytitie intersection
The excavation works currently underway on Hakunilantie will expand to the section between Raudikkokuja and Kyytitie in week 28. Drilling and trench excavation will be carried out in the area, causing significant noise.
Blasting works will affect parking and traffic near Laukkarinne and Kyytitie during week 28
Blasting work will be carried out during the daytime in week 28 in the area connecting Laukkarinne and Kyytitie. The work requires the nearby parking area to be cleared and will cause short traffic interruptions during blasting.
Temporary Traffic Arrangements Introduced on Lemmenkuja
Construction works at the Vaarala depot have progressed to Lemmenkuja, and from week 26 onwards, temporary traffic arrangements have been implemented. These arrangements will be modified as the work progresses.
Introduction of a temporary access ramp to Tikkuparkki
Construction of the Vantaa light rail is ongoing in Kirjastopuisto. According to current plans, a temporary access ramp to Tikkuparkki will be introduced on 10 July. It is located next to the current ramp, closer to the library. Tikkuparkki will operate as normal throughout the construction period.
Through traffic on Ratatie is closed to all traffic at Ratakuja from 27 July to 31 August.
Vantaa light rail works will continue in Tikkurila during the summer. Through traffic on Ratatie will be closed to all traffic from 27 July to 31 August. During this time, a bridge will be installed on Ratatie over Ratakuja, under which the light rail tunnel will be constructed.
Pedestrian overpasses on Hakunilantie to be demolished in June – works carried out at night
The demolition of the pedestrian overpasses on Hakunilantie at Hakunila shopping centre (Kaviopolku), Raudikkopolku, and Hevoshaanpolku will be carried out in three phases in June. The work will take place at night. The demolition is not expected to cause significant noise in the area.
Pedestrian and cycling routes on Aviabulevardi will change
The pedestrian and cycling route on Aviabulevardi will be closed during the week starting 22 June. An alternative route is available via Turbiinitie. Aviabulevardi was closed to vehicle traffic in May.
The Vantaa light rail construction site expands at the intersection of Tikkurilantie and Puutarhatie
The Vantaa tramway worksite will expand at the intersection of Tikkurilantie and Puutarhatie during the week starting June 22. The pedestrian and cycling path located on the north side of Tikkurilantie will be taken out of use for a distance of a few hundred meters. An alternative pedestrian and
Ground stabilization work causing significant noise will begin in June at the southern end of Hakunilantie
Ground stabilization works will begin at the southern end of Hakunilantie in week 26. The work is estimated to continue until the end of August 2026. The work will cause significant noise in the area as well as changes to traffic arrangements. As part of these changes, the bus stop on Vaaralantie
Noisy work phases planned on the median strip of Porvoonväylä at Länsimäentie and in the Maratontie area in July–August
On the Porvoonväylä at the intersection with Länsimäentie and near the Maratontie roundabout, work will be carried out during the summer that will cause noise. At the turn of June and July, rock blasting will take place in the central lanes, which may result in loud noise and temporary traffic