Service group: Transport
Vantaa Light Rail Work Site to Expand on Kielotie in April
Construction of the Vantaa tram is progressing on Kielotie. After Easter, starting on April 7, the construction site will expand southward from Unikkotie to Neilikkatie. Motor vehicle traffic will be removed from this section of Kielotie, and alternative driving routes will be via Talvikkitie and
Changes in Tikkurilantie traffic arrangements starting April 7, 2026
The foundation work for the Vantaa light rail is progressing on Tikkurilantie. Due to new construction phases, the section between Osmankäämintie and Talvikkitie will be completely closed to through traffic. At the same time, Osmankäämintie will be opened for traffic crossing Tikkurilantie. Vehicles
Construction of the Vantaa Light Rail Begins on Hakunilantie and Tilustie
Construction will begin during April at three locations. Preparatory works will start in stages on Hakunilantie, Tilustie and on the new street connection, Rivieranraitti. The works will cause temporary changes to traffic arrangements.
Vantaa will become a modern and attractive light rail city
For many Vantaa residents, the light rail will mean smoother mobility in everyday life in the future. But that’s not all – an entire light rail city will be built around the light rail.
Construction of the light rail in Tikkurila Center and Jokiniemi
Follow the progress of light rail construction in the area around Kielotie, Tikkurila station and Jokiniemenkatu. You can also explore current diversion routes and read the latest news about the worksites.
Construction of the light rail from Aviapolis Station to Rälssitie
Follow the progress of light rail construction between Aviapolis Station and Rälssitie. The continuation of the light rail from Aviapolis Station to the airport and its final end station will be decided later.
Construction of the Light Rail from Hakunila to Fazerila
Follow the progress of light rail construction in Hakunila, Vaarala and Fazerila.
Construction of the light rail on Kyytitie
Follow the progress of light rail construction between the Heidehof traffic circle and Hakunilantie.
Traffic routes in Virkamies will change starting 9 March
The construction of the Vantaa Light Rail is progressing in the Virkamies area. Through traffic on Toinen savu will be cut off on 9 March. Alternative vehicle routes are via Pakkalantie and Lentoasemantie.
Blasting works will begin in Kirjastopuisto
Blasting works for the Vantaa Light Rail will begin in Kirjastopuisto next week. The estimated duration of the works is 23.2–30.04. Some stages of the work will cause noise.