Service group: Transport
Heavy Traffic in Vantaa
One of the goals of Vantaa’s transport policy program is to ensure the smooth operation of freight traffic on main routes and to support delivery traffic in city centers.
Geotechnical fieldwork related to the Vantaa Light Rail project will begin in early November 2025 on Länsimäentie, in the areas of Vantaa and Helsinki
In early November, trial ground stabilization will start on Länsimäentie at the border between Vantaa and Helsinki. The purpose of these tests is to determine the most suitable and cost-effective soil reinforcement method for the area before the main construction begins. Work will start in week 45
The Ratatie P1 park-and-ride facility will be closed at the end of October
The P1 park-and-ride facility located on Ratatie, north of Tikkurila Station, will be closed during the week starting October 27.
Construction of the Vantaa Light Rail begins on 1 December 2025 between Kuninkaala and Mellunmäki – Invitation to a resident meeting
Construction work on the Vantaa Light Rail between Kuninkaala and Mellunmäki will begin in December 2025 on several sections simultaneously. We will provide more detailed information on the construction work and possible temporary routes for each area closer to the start of construction. A public
Construction of the Vantaa Light Rail to Begin on Tikkurilantie in December
According to current plans, construction of the Vantaa Light Rail will begin on Tikkurilantie on December 1st. Work will take place between Puutarhatie and Kielotie, and this section will be gradually taken out of use for vehicular traffic starting in December and continuing through January.
Interruptions to rail traffic will continue in the Tikkurila station
Interruptions to rail traffic will continue in the Tikkurila station Banavbrotten fortsätter vid Dickursby station. Track 1 will be out of use from 27 October to 12 December. Please check the departure platforms of the trains on the station's information displays.
Preparatory work on the Vantaa Light Rail to begin on Peltolantie and Puutarhatie
Preparatory works for the Vantaa light rail will begin on Puutarhatie between Tikkurilantie and Peltolantie, and on Peltolantie between Puutarhatie and Osmankäämintie. The works are scheduled to start at the end of September and be completed by early November
Work on the Vantaa Light Rail continues — tracks 3 and 4 will be out of use from 5 September to 17 October in the Tikkurila station area
Preparatory work on the Vantaa Light Rail will continue in the Tikkurila station area. Track 2 will be out of use from 5 September to 17 October. Noisy construction work will be carried out around the clock between September 19 and 8 October. Tikkurila station will operate as normal throughout this
Preparatory work on the light rail tunnel to be expanded: Kielotie between Asematie and Lummekuja, along with Kirjastopuisto, will become a work site in September
The preparatory work on the Tikkurila light rail tunnel will be expanded at the beginning of September. Kielotie between Asematie and Lummekuja, along with Kirjastopuisto, will become a work site starting from 1 September 2025.
Work on the Vantaa Light Rail continues — tracks 3 and 4 will be out of use from 28 July to 5 September in the Tikkurila station area
Preparatory work on the Vantaa Light Rail will continue in the Tikkurila station area. Tracks 3 and 4 will be out of use from 28 July to 5 September 2025. Noisy construction work will be carried out around the clock between 3 August and 16 August 2025. Tikkurila station will operate as normal