Tag: Vantaa Light Rail Kuninkaala - Mellunmäki
Noisy Drilling and Rock Excavation Works to Begin on Rivieranraitio
Rock and stone drilling as well as rock excavation works will begin in September along the future tramway street connection on the Rivieranraitio. The works will cause significant noise in the area. The works are scheduled to start in Week 36.
Gas pipeline construction work continues in Heidehof Park – changes to pedestrian routes as work progresses
In addition to the construction of the Vantaa light rail, preparatory and construction works related to gas transmission company Gasgrid’s high-pressure gas pipeline, as well as the construction of a pressure reduction station, will be carried out in the area during weeks 35–46.
Changes to pedestrian, cycling and bus stop arrangements on Länsimäentie during week 36
Traffic arrangements on Länsimäentie will change next week in the area around the roundabout at Maratontie and Länsimäentie.
Construction Works for the Vantaa Light Rail Begin at Ring III Near the Hakunilantie Bridge
Construction of the Vantaa Light Rail project is progressing in the Hakunilantie and Ring III area. The existing Hakunilantie bridge crossing Ring III will be replaced with a new bridge that will accommodate both road traffic and light rail services in the future.
Bus stop changes in Hakunila – Raudikkopolku stop V9417 replaces Hevoshaanpolku stop V9419
As the Vantaa Light Rail construction progresses, the temporary bus stop arrangements on Hakunilantie are being removed in phases. The temporary Hevoshaanpolku stop (V9419) on Hakunilantie will be taken out of service on 20 August 2026. At the same time, the Raudikkopolku stop (V9417) will be
Two Push-Button Pedestrian Crossings on Hakunilantie from 3 August
Two new push-button traffic signals will be introduced in Hakunila on Monday, 3 August 2026, as part of the traffic arrangements related to the construction of the Vantaa Light Rail. The new pedestrian crossing signals are intended to improve the safety of schoolchildren and other pedestrians
Construction of the Vantaa Light Rail Begins on Fazerintie and Rivieranraitio
Construction of the Vantaa Light Rail will start in the Rivieranraitio and Fazerintie area on 3 August. The first phase includes a site inspection and tree felling, after which municipal infrastructure, site fencing and temporary diversion routes will be built in the area.
Rock blasting works on Länsimäentie between Ring III and Fazerintie, week 33
Rock blasting works will continue on Länsimäentie, on the section between Ring III and Fazerintie, week 33
Gas Pipeline Construction Begins on Käärmekalliontie in Week 31
Käärmekalliontie will undergo construction of a new gas pipeline starting in week 31. The work is scheduled to take place during the shutdown period of the incineration plant, which means that, exceptionally, some work will also be carried out during the evenings and on weekends over the coming
Part of Kyytitie to close from 27 July – traffic diverted for approximately two months
Traffic arrangements on Kyytitie near Kaskela will change from 27 July due to the construction of Vantaa Light Rail. For approximately two months, a section of Kyytitie will be closed, and both vehicle traffic and bus services will be diverted via Pitkäsentie and the Lahdentie ramp.