Tag: Vantaa Light Rail Kuninkaala - Mellunmäki
Vanha Porvoontie will reopen to traffic on 23 February 2026 – changes to traffic arrangements at the intersection of Sammaltie and Kyytitie
The concrete culvert found beneath Vanha Porvoontie has been demolished. A new stormwater line, district heating line and cable ducts have been installed at the roadway. The intersection area will reopen to vehicular traffic on 23 February 2026. Once the intersection is reopened, construction work
Kyytitie between Heidehofintie–Sammaltie/Kanervantie will be closed to vehicle traffic from 2 March 2026 – the closure will last until the end of August 2027
Ground reinforcement works, relocation of municipal utilities, and construction of a new bridge and track for the future tramway will begin on Kyytitie. As a result, Kyytitie will be closed to vehicle traffic between Heidehofintie–Sammaltie/Kanervantie from 2 March 2026. Access to the Neste station
Construction phases causing especially loud noise will begin on Kyytitie in late February and early March
In late February and early March, construction work causing especially loud noise will take place along Kyytitie in the northern part of Porttipuisto and near Heidehof Park.
Invitation to Resident Information Sessions – Construction of the Vantaa Light Rail Begins on Hakunilantie
According to current plans, construction of the Vantaa Light Rail will begin on Hakunilantie in spring 2026. We will organise resident information sessions about the upcoming street construction works: one in Vaarala Chapel (Kirkkokuja 2) on 23 February from 18:00 to 19:00, and another in
The closure of Vanha Porvoontie between Kyytitie and Kokkokalliontie will last longer than announced – the road will reopen to vehicle traffic on 23 February 2026
Vanha Porvoontie between Kyytitie and Kokkokalliontie had to be closed due to an old concrete duct discovered in the intersection area. The duct had been marked as removed, but excavation revealed that it remains in place over a long distance.
Vanha Porvoontie will be closed to car traffic between Kyytitie and Kokkokalliontie from 19 January to 6 February 2026
Vanha Porvoontie will have to be closed to car traffic between Kyytitie and Kokkokalliontie for the period 19 January–6 February 2026. During the closure, bus and car traffic will be directed to use Kyytitie and Kanervatie.
Service Disruption Notice! Telecommunications cable damaged on Kyytitie
During construction work on Kyytitie, a telecommunications cable was damaged. This is causing disruptions to internet connectivity in the Kuusikko, Hakkilankallio and Porttipuisto areas. Problems have been reported at least with Elisa’s connections. Repair work is currently underway, and we will
The bridge over Porvoonväylä on Länsimäentie (Västerkullavägen) will become single-lane starting 2 February 2026 – construction work will cause special noise in the area.
Construction of a new bridge over Porvoonväylä will begin at the location of the current bridge. The work will start with the building of temporary support walls, including excavation and sheet piling. These works will cause special noise in the surrounding area. Due to the construction, the bridge
The news has been updated – The roundabout at Kyytitie and Porttisuontie will be converted into a signal-controlled intersection on 30 January 2026.
The roundabout intersection at Kyytitie and Porttisuontie will be converted into a signal-controlled junction 30 January 2026. The number of driving lanes will remain the same despite the change. However, as the work progresses, there may be some temporary changes to the lanes in the area, so please
Pelto-oja Road closed to vehicle traffic from 12 January 2026
Pelto-oja Road closed to vehicle traffic from 12 January 2026. The closure will last for two years.