The Kyytitie street section between Jokiniemenkatu and Kanervantie to open to traffic eight months ahead of schedule
Construction of the Vantaa light rail is progressing ahead of schedule on Kyytitie. The street section between Jokiniemenkatu and Kanervantie, built by the East Alliance formed by Kreate and GRK, will open to traffic on Monday, 7 December 2026. The street will be brought into use as much as eight
Water Main Drilling Works to Begin on Fazerintie in Week 47
A water main will be constructed beneath Fazerintie during week 47. The work will be carried out using a percussion drilling method, which allows the water main to be installed under the road without extensive excavation of the street or major traffic arrangements.
Piling works causing significant noise to begin in week 47 on Hakunilantie south of Ring III
Piling works will commence in week 47 on Hakunilantie, south of Ring III. The work phase will cause intermittent noise and vibration in the vicinity of the work area during November and December.
Water Utility Works Expand – Vaarala Talkootie Bus Stop Relocates from 11 November
The Vaarala Talkootie bus stop will be temporarily relocated to a new location starting Wednesday, 11 November. The stop is being moved due to the expansion of the work area for ongoing water utility construction works. The temporary stop will be located approximately 60 metres back in the direction
Noisy construction work continues on Länsimäentie next week
Next week (week 46), the previous sheet piling works will be followed by piling works as part of the construction of the water and sewer network.
Removal of the temporary fencing at Länsimäki Dog Park to begin on Monday, 2 November 2026 – temporary closure
The removal of the temporary fencing at Länsimäki Dog Park will begin on Monday, 2 November 2026. In addition to the removal work, construction work related to the restoration of the area will be carried out at the dog park until Wednesday, 4 November 2026.
Construction Works Progress at the Hakunilantie Bridge Site – Temporary Traffic Arrangements to Be Introduced on Ring Road III
Construction works related to the replacement of the Hakunilantie bridge are progressing, and the implementation of temporary traffic arrangements on Ring Road III will begin in week 42. The arrangements will be introduced in phases and will be fully in place by week 44. Two traffic lanes in each
Work Causing Elevated Noise Levels to Begin on Länsimäentie
Construction of the Vantaa Tram is progressing on Länsimäentie. Starting in week 44, several work phases that generate elevated noise levels will begin near the intersection of Keihästie and Pallastunturintie. The works are related to the construction of future water supply infrastructure and will
Municipal Infrastructure and Foundations Under Construction at the Vaarala Depot, Pedestrian and Cycling Connections Reopened
Rock excavation and crushing works at the Vaarala depot have been completed, and construction has now progressed to municipal infrastructure and depot structure works. The pedestrian and cycling connection via Lemmenkuja has been reopened following the completion of construction works, and temporary
Changes to traffic arrangements on Hakunilantie at the Hevoshaantie underpass
Rehabilitation works on the western side of the Hevoshaantie underpass have been completed, and construction will now move to the eastern side of the underpass. Traffic arrangements required for the new construction phase will be implemented in week 43, when traffic will be shifted to the western