The Kyytitie street section between Jokiniemenkatu and Kanervantie to open to traffic eight months ahead of schedule

News

Tags

Tikkurila major region

Construction of the Vantaa light rail is progressing ahead of schedule on Kyytitie. The street section between Jokiniemenkatu and Kanervantie, built by the East Alliance formed by Kreate and GRK, will open to traffic on Monday, 7 December 2026. The street will be brought into use as much as eight months ahead of the original schedule.

kyytitie-avautuminen

Construction of the Kyytitie street section near Heidehof Park began in December 2025. According to the original schedule, the section between Jokiniemenkatu and Kanervantie was due to be completed in spring 2027. However, thanks to smooth planning, effective cooperation and skilled construction work, the street can now be opened to traffic as early as December 2026.

The opening of the street section will restore traffic on Kyytitie to its original route. At the same time, the temporary diversion via Santaradantie and Kanervikkotie will be discontinued.

“This kind of significant schedule achievement is not the result of individual successes, but of seamless cooperation across the entire team. On Kyytitie, design and construction have worked hand in hand, and solutions have been implemented smoothly as the work has progressed. Cooperation between GRK and Kreate within the East Alliance has worked exceptionally well. The joint efforts of designers, site management and construction teams have made it possible to complete even a challenging construction site ahead of schedule,” says Antti Saikkonen, Production Manager of the East Alliance.

Jani Jortama, Project Manager for the Kyytitie sub-project, also praises the successful cooperation and strong performance on site.

“The site management and construction teams have done a really good job. Credit is also due to the designers from the different technical disciplines, who have gone the extra mile to ensure that the construction site can operate efficiently. It has been great to see how well everyone has worked together towards a common goal,” Jortama says.

Although the street will open to traffic already in December, finishing work on the surface structures and landscaping will continue in the area next spring. These works will not cause any significant changes to arrangements for motor vehicle traffic, pedestrians or cyclists. However, there may be brief traffic stoppages at the construction site, with traffic controllers ensuring that traffic continues to flow smoothly.

The next section of Kyytitie to close in February 2027

Construction of the Vantaa light rail will continue along Kyytitie towards Hakunila. The next section to close to motor vehicle traffic will be the stretch of Kyytitie between Kanervantie and Vanha Porvoontie, starting on Monday, 1 February 2027. The street area is expected to remain closed for approximately one year.

More detailed information about diversion routes for motor vehicles, pedestrians and cyclists will be provided closer to the start of the closure. The main goods vehicle entrance to Kesko's central warehouse has already been relocated from Kyytitie to Kanervantie.

Read more about Bus services here.