Tikkurila major region
Blasting works will begin in Kirjastopuisto
Blasting works for the Vantaa Light Rail will begin in Kirjastopuisto next week. The estimated duration of the works is 23.2–30.04. Some stages of the work will cause noise.
Vanha Porvoontie will reopen to traffic on 23 February 2026 – changes to traffic arrangements at the intersection of Sammaltie and Kyytitie
The concrete culvert found beneath Vanha Porvoontie has been demolished. A new stormwater line, district heating line and cable ducts have been installed at the roadway. The intersection area will reopen to vehicular traffic on 23 February 2026. Once the intersection is reopened, construction work
Kyytitie between Heidehofintie–Sammaltie/Kanervantie will be closed to vehicle traffic from 2 March 2026 – the closure will last until the end of August 2027
Ground reinforcement works, relocation of municipal utilities, and construction of a new bridge and track for the future tramway will begin on Kyytitie. As a result, Kyytitie will be closed to vehicle traffic between Heidehofintie–Sammaltie/Kanervantie from 2 March 2026. Access to the Neste station
Construction phases causing especially loud noise will begin on Kyytitie in late February and early March
In late February and early March, construction work causing especially loud noise will take place along Kyytitie in the northern part of Porttipuisto and near Heidehof Park.
Vanha Porvoontie will be closed to car traffic between Kyytitie and Kokkokalliontie from 19 January to 6 February 2026
Vanha Porvoontie will have to be closed to car traffic between Kyytitie and Kokkokalliontie for the period 19 January–6 February 2026. During the closure, bus and car traffic will be directed to use Kyytitie and Kanervatie.
Service Disruption Notice! Telecommunications cable damaged on Kyytitie
During construction work on Kyytitie, a telecommunications cable was damaged. This is causing disruptions to internet connectivity in the Kuusikko, Hakkilankallio and Porttipuisto areas. Problems have been reported at least with Elisa’s connections. Repair work is currently underway, and we will
The news has been updated – The roundabout at Kyytitie and Porttisuontie will be converted into a signal-controlled intersection on 30 January 2026.
The roundabout intersection at Kyytitie and Porttisuontie will be converted into a signal-controlled junction 30 January 2026. The number of driving lanes will remain the same despite the change. However, as the work progresses, there may be some temporary changes to the lanes in the area, so please
New construction sites for the Vantaa light rail in the Väritehtaankatu area
The construction work for the Vantaa light rail is expanding in the Väritehtaankatu area. Some sections have already been fenced off for site use, and the work will begin with the relocation of municipal infrastructure. Work on the site will take place on weekdays between 7 a.m. and 6 p.m.
Pedestrian and bicycle traffic will be closed on Kielotie between Asematie and Unikkotie
Pedestrian and cycle traffic will be closed on Kielotie between Asematie and Unikkotie due to the relocation of municipal infrastructure. All local shops and businesses will remain open as usual.
Through‑traffic on Ratatie will come to an end
Construction of the Vantaa Light Rail is progressing in Tikkurila. Through‑traffic on Ratatie will end on 19 January, and at that time we will begin building new bus stops. The works are related to the construction of the light rail tunnel.