Vantaa Light Rail Work Site to Expand on Kielotie in April

News

Construction of the Vantaa tram is progressing on Kielotie. After Easter, starting on April 7, the construction site will expand southward from Unikkotie to Neilikkatie. Motor vehicle traffic will be removed from this section of Kielotie, and alternative driving routes will be via Talvikkitie and

Tikkurila major region

Changes in Tikkurilantie traffic arrangements starting April 7, 2026

News

The foundation work for the Vantaa light rail is progressing on Tikkurilantie. Due to new construction phases, the section between Osmankäämintie and Talvikkitie will be completely closed to through traffic. At the same time, Osmankäämintie will be opened for traffic crossing Tikkurilantie. Vehicles

Tikkurila major region

Construction of the Vantaa Light Rail Begins on Hakunilantie and Tilustie

News

Construction will begin during April at three locations. Preparatory works will start in stages on Hakunilantie, Tilustie and on the new street connection, Rivieranraitti. The works will cause temporary changes to traffic arrangements.

Hakunila major region

Vantaa will become a modern and attractive light rail city

Article

For many Vantaa residents, the light rail will mean smoother mobility in everyday life in the future. But that’s not all – an entire light rail city will be built around the light rail.

Aviapolis major region Hakunila major region Tikkurila major region

Construction of the light rail on Länsimäentie

Project

Follow the progress of light rail construction from Fazerila to Mellunmäki. In the future, the light rail will run along Länsimäentie to the Mellunmäki metro station.

Hakunila major region

Traffic routes in Virkamies will change starting 9 March

News

The construction of the Vantaa Light Rail is progressing in the Virkamies area. Through traffic on Toinen savu will be cut off on 9 March. Alternative vehicle routes are via Pakkalantie and Lentoasemantie.

Aviapolis major region

Blasting works will begin in Kirjastopuisto

News

Blasting works for the Vantaa Light Rail will begin in Kirjastopuisto next week. The estimated duration of the works is 23.2–30.04. Some stages of the work will cause noise.

Tikkurila major region

Vanha Porvoontie will reopen to traffic on 23 February 2026 – changes to traffic arrangements at the intersection of Sammaltie and Kyytitie

News

The concrete culvert found beneath Vanha Porvoontie has been demolished. A new stormwater line, district heating line and cable ducts have been installed at the roadway. The intersection area will reopen to vehicular traffic on 23 February 2026. Once the intersection is reopened, construction work

Hakunila major region Tikkurila major region

Bus routes in the Pakkala area will change starting from 2 March

News

Bus routes in the Pakkala area will change starting from 2 March. Toinen Savu will be closed to through‑traffic. Bus 600 will be rerouted to Pakkalantie, and bus 570 to Lentoasemantie.

Aviapolis major region

Invitation to Resident Information Sessions – Construction of the Vantaa Light Rail Begins on Hakunilantie

News

According to current plans, construction of the Vantaa Light Rail will begin on Hakunilantie in spring 2026. We will organise resident information sessions about the upcoming street construction works: one in Vaarala Chapel (Kirkkokuja 2) on 23 February from 18:00 to 19:00, and another in

Hakunila major region