Construction of the light rail in Tikkurila Center and Jokiniemi

Follow the progress of light rail construction in the area around Kielotie, Tikkurila station and Jokiniemenkatu. You can also explore current diversion routes and read the latest news about the worksites.

  • Project status
    Ongoing
  • Project schedule
    -
Tikkurila tunnel worksite in the aerial image.

Vantaa light rail construction site in Tikkurila.

The Vantaa light rail will run smoothly in a tunnel beneath Tikkurila station, the public transport terminal, Ratatie and Kirjastopuisto. The stop located in the tunnel beneath Tikkurila station is expected to be the busiest on the entire light rail line in terms of passenger numbers. Preparatory works in Tikkurila already began in May 2025.

Light rail worksite areas and traffic arrangements

Vantaa Map Service

Progress of construction

Information will be updated as construction progresses. The preliminary schedule may change, for example due to weather conditions. We will provide more detailed information on upcoming work phases closer to their start. The page also includes links to news items where you can read more about current developments in the area.


Updated 26 November 2026.

 

• Preparatory works began at Tikkurila Station in May 2025.
• During 2025, all tracks at Tikkurila Station were moved onto temporary bridges. Tunnel construction is currently progressing beneath them.
• Worksites are now active along almost the entire route. The current traffic arrangements have largely been established.
• The tunnel worksite, which is critical to the overall project schedule, has progressed on schedule. For example, concrete works began slightly ahead of schedule.

Kielotie

• Track foundation works ongoing.
• The first light rail tracks were installed on 18 November 2026.
• The light rail worksite will expand south of Neilikkatie in January 2027.
• According to current plans, Kielotie will reopen to vehicle traffic in summer 2028.

Lummekuja and Kirjastopuisto

• Intermittent rock excavation works will continue in Kirjastopuisto during the winter.
• Tunnel concrete works began ahead of schedule in autumn 2026.

Ratakuja, Ratatie and Dixi

• Modification and support works required at Dixi.
• Excavation works and utility relocations ongoing.
• Rock sawing works ongoing.
• Rock excavation works in spring 2027.
• Tunnel concrete works will begin later in spring 2027.

Main Railway Line and Väritehtaankatu Area

• Tunnel concrete works began in autumn 2026.

Jokiniemenkatu and Keravanjoki Area

• Municipal engineering relocations and excavation works ongoing around the Keravanjoki area.
• Construction of the Keravanjoki bridge worksite begins in February 2027.

More information

Light Rail Team

ratikka@vantaa.fi

Feedback and questions related to Vantaa light rail and the construction of the light rail