Construction of the light rail on Länsimäentie

Follow the progress of light rail construction from Fazerila to Mellunmäki. In the future, the light rail will run along Länsimäentie to the Mellunmäki metro station.

Project status
Ongoing
Project schedule
-
Länsimäentiellä melutöitä.

The construction sites on Länsimäentie are in the areas of Vaarala and Länsimäki, near Rajakylä.

Light rail worksite areas and traffic arrangements

Vantaa Map Service

Progress of construction

Information will be updated as construction progresses. The preliminary schedule may change due to weather conditions, for example.

Information updated 26.6.2026

June–August 2026

  • At the northern end of Länsimäentie, relocation works for municipal infrastructure, water pipelines, gas and electricity are being carried out, resulting in minor changes to traffic lanes.
  • The section of Länsimäentie between Rajakentäntie and Keihästie is closed to traffic. Traffic has been redirected via Pallastunturintie. The arrangement also applies to bus routes that previously operated along Länsimäentie. The street section will remain closed and the detour in use until September 2027.
  • The first tram tracks for the Länsimäentie section will be installed near the intersection of Länsimäentie and Fazerintie in July 2026.
  • Construction work on the bridge crossing Porvoonväylä is underway.

Noisy work in June–August 2026

  • Sheet piling works will begin near the bridge crossing Porvoonväylä, and blasting work is also underway in the surrounding area.