Follow the progress of light rail construction between Aviapolis Station and Rälssitie. The construction sites are located in Aviapolis, Veromies and Pakkala. In the future, the light rail will travel from the airport to Pakkala, passing through Jumbo and the new aviation museum, among other stops.
The first tracks of the Vantaa light rail were installed at the Plootukallio worksite on 11 May 2026.
Light rail worksite areas and traffic arrangements
Construction progress
Information will be updated as construction progresses. The preliminary schedule may change, for example due to weather conditions. We will provide more detailed information on upcoming work phases closer to their start. The page also includes links to news items where you can read more about current developments in the area.
Information updated on 8 September 2026.
- Work on the subproject began at Plootukallio in December 2025.
- Worksites are currently active on Aviabulevardi, Plootukallio, Toinen savu, Osuustie and Elannontie.
- Next, works will expand southwards along Osuustie during autumn 2026 and to Ilmailuaukio in December 2026.
- Construction will begin on Tasetie in January 2027, at the northern end of Rälssitie in spring 2027, and on Väinö Tannerin tie in late summer 2027.
- The Osuustie–Virkatie–Antaksentie section will open during winter 2027–2028.
- In the final layout, Toinen savu and Aviabulevardi will function as public transport streets.